Hubbard Farms Neighborhood Association Agenda
October 17, 2023, 6:30pm-8:00pm
Recording: https://fathom.video/calls/43469415
- Welcome and Introductions
- Board members: Marlena Hanlon, Nat Zorach, Zeb Smith
- Terming-out board members: Mike Smith, Adriana Zuniga
- Residents – Devon Caldwell (also Inkwell), Louisa Howard
- Others: Joel RK (CM Santiago-Romero), Ryan Zampardo (Inkwell), Tim Flintoff (4545 Architecture), Josh Maddox (4545 Architecture)
- Board members: Marlena Hanlon, Nat Zorach, Zeb Smith
- Approval of Minutes
- Old Business
- New members! Marlena, Nat, Monte Martinez, Caton Arreguin
- Returning members: Myett Risker, Zeb Smith
- Terming out: Mike Smith (resigned), Adriana Zuniga, Mary Clare Duran, Phil Clark
- Elections – officers to be decided 10/19/23
- New Business
- W. Grand and Porter update (Inkwell)
- 11 units still, 8 on W. Grand, 3 on Porter.
- Tried to minimize large surface parking in back based on City feedback.
- 4 with parking in back, 7 with parking underneath.
- Reaction to City feedback:
- Set back northern segment on W. Grand to align with housing north.
- New brick color scheme for this northern section.
- Wood accents around balconies/entry doors.
- Going before BZA at end of October to get approval for a few of the variances.
- How close it is to lot lines.
- Lot coverage of site.
- Next steps:
- Submitted for BSEED permits.
- BZA
- NEZ application
- Final pricing/financing
- Construction start
- Feedback:
- Marlena – resiliency and water runoff/retention.
- Including catch basins underground.
- Pervious pavement – City won’t count it here towards parking right now although they did elsewhere in city.
- Break ground – during warmer months after thaw passes (around April), construction in 18-month timeframe. Comps 14-18 months.
- Marlena – resiliency and water runoff/retention.
- Broderick Manor
- A lot of internal work in the last year. Stabilized interior that had four-story collapse. New historic windows mostly in.
- 90% through rough carpentry. Over 300 joists to make building structurally sound.
- New roof.
- Reinstalled water meter and main lines in. Working through final power with DTE.
- Got permits and HDC approvals.
- Big item:
- Still need to close construction loan. Should close that by the end of the year. Complicated loan with multiple lender parties.
- Still have to discuss lot use with community after official closing.
- 56 units.
- Questions:
- How did this get by parking minimums?
- Grandfathered into zero parking requirements.
- How did this get by parking minimums?
- W. Grand and Porter update (Inkwell)
- Committee Updates
- Neighborhood Beautification Committee
- Communications Committee
- Next steps:
- Ascertain to how to get social media done.
- Reorganize/organize front page of website to make it clear how to connect to committees and board members.
- Next steps:
- Resident and Attendee Issues
- Joel – Building Power training series at 6pm 10/18. CBA – learn more and organize in communities.
- Coffee hour – Thursday 10/24 @ 2pm @ UNI on Lawndale.